Overview
- Chief Minister N. Chandrababu Naidu on Wednesday reviewed the energy sector and directed officials to prepare operationally for a projected peak demand of 14,852 MW within the next six months.
- State officials said electricity consumption rose 18.23% from April to November and attributed the jump largely to El Niño‑related higher temperatures increasing cooling and irrigation load.
- The government is advancing Green Energy Corridor‑III, a proposed ₹21,838 crore transmission plan meant to evacuate up to 47 GW of renewables, to handle growing solar capacity.
- Plans also include 27 identified pumped‑storage sites near Polavaram with a combined proposed capacity of 36,050 MW to add large‑scale grid balancing and storage capacity.
- Since June 2024 the state has approved 103 energy projects (proposed ₹4.20 lakh crore) and secured ₹2.56 lakh crore in CII summit agreements, while rooftop solar and PM‑KUSUM projects report substantial installation and civil‑works progress.