Particle.news

Amazon Withdraws Ashburn Data Center Plan After Deal With Loudoun County

The agreement commits roughly 25 acres for community facilities plus $5 million to affordable housing as Loudoun weighs a one‑year pause on new data‑center applications.

Overview

  • A deal announced Thursday between Amazon and Loudoun County called Project Potomac Promise has Amazon withdrawing its site plan for four data centers on the former George Washington University campus and dropping plans to sue over the property.
  • Under the agreement Amazon will donate about 25 acres for public facilities and contribute $5 million to the county’s affordable housing trust fund while pursuing rezoning of the remaining land for mixed use.
  • Amazon has also taken companywide steps to increase openness, including stopping the practice of asking local officials to sign nondisclosure agreements before projects become public.
  • Tensions that produced the deal grew from resident complaints about noise, visual impacts, and strains on power and water supplies and from reporting that local governments had offered large water allocations to developers.
  • Local leaders are now considering a one‑year pause on new data‑center applications, a move that could reshape review rules and how future projects are negotiated in Northern Virginia.