- Provincial amendments tabled to Bill 8 would let large AI data centres bring on-site or dedicated generation and receive expedited approvals.
- Projects connecting to the grid would be required to pay for any necessary transmission upgrades rather than passing costs to ratepayers.
- The plan advances Alberta’s Restructured Energy Market, with broader market changes targeted to start taking effect in 2027.
- The Alberta Electric System Operator has set a 1,200 MW interim allocation for data-centre connections and is developing a long-term integration framework.
- Complementary measures include updates to transmission policy that recognize incumbent generators and rules to enable hydrogen-blended natural gas pilot projects.