Air Force Sets Mid-2028 Delivery for First New Air Force One After Approving Communications Upgrade

A $15.5 million communications upgrade will be integrated without changing the program’s schedule.

Overview

  • An Air Force spokesperson confirmed the first VC-25B is now targeted for delivery in mid-2028, earlier than the previously signaled 2028–2029 window.
  • The service added $15.5 million for upgraded communications on both aircraft, a modification it says fits within the current plan.
  • The change lifts the total contract value to more than $4.3 billion and is separate from the firm-fixed-price engineering and manufacturing development work.
  • The communications integration is expected to be finished by December 2026, according to the Air Force.
  • In parallel, the administration is pursuing a retrofit of a Qatar-donated 747 as an interim option, with officials citing a sub-$400 million cost and funding shifted from the Sentinel ICBM program.