  • Operations were halted from roughly 14:00 to 17:00 after asphalt detached near cabecera 31 during a takeoff, triggering safety protocols to prevent engine ingestion of debris.
  • By 16:00, official data showed 8 flights diverted and 10 delayed arrivals, with about 10 departures also showing delays and gate changes.
  • Aerolíneas Argentinas reported 14 delayed flights and 7 arrivals diverted to Ezeiza during the interruption, with other carriers also affected.
  • Authorities said the damaged area was adjacent to the runway rather than the central surface, and flights resumed progressively with residual delays from diversions and schedule knock-ons.