Overview
- AESL announced on Thursday that it secured the 'Evacuation of Power from 3X800 MW STPP Pirpainti' contract and will execute the work through a new SPV, Vikramshila Power Transmission Limited.
- The project scope requires adding 881 circuit kilometres of transmission lines and 3,160 MVA of transformation capacity, including four gas-insulated substations at Jhanjharpur, Bethauli and Begusarai.
- AESL said the work will include multiple 400 kV double-circuit and 220 kV lines plus line bays at Bakhtiyarpur to enable reliable evacuation of 2,400 MW from the Pirpainti thermal plant.
- The company projects an annual tariff of about ₹500 crore once commissioned and says the award raises its cumulative network to 30,683 ckm and its transmission capex pipeline to roughly ₹91,500 crore.
- AESL expects to complete the transmission build by the final quarter of 2028, a timeline that could affect regional grid capacity, local construction employment and the schedule for bringing Pirpainti's generation fully online.