ACME Solar Holdings Brings Surendranagar Wind Project to 44 MW With Second-Phase Commissioning

The phased build proceeds under a regulator-approved extension that sets the SCOD at March 5, 2026.

Overview

  • The company commissioned an additional 16 MW at its 100 MW site in Surendranagar, taking early operational capacity to 44 MW.
  • The first 28 MW entered service in October 2025, with the remaining capacity scheduled to be added in phases.
  • Power from the project will be sold under a 25-year PPA between ACME Eco Clean and Gujarat Urja Vikas Nigam Ltd.
  • Financing is provided by Power Finance Corporation, and officials from GEDA and PGVCL witnessed and confirmed the partial commissioning.
  • ACME reports 2,934 MW operational across its portfolio, with 4,456 MW under construction including 13.5 GWh of battery energy storage.