- The A99 will be fully closed between Autobahnkreuz München-Süd and München-Ost from Friday, 20 November at 20:00 until Monday, 23 November at 05:00, with preparatory work from about 18:00 and the controlled one-piece demolition planned around 22:00 on Friday.
- Authorities say the bridge is so structurally degraded that only a single-piece removal can prevent the remaining structure from collapsing onto the motorway, so a staged partial demolition was ruled out for safety.
- Traffic disruption is expected across the entire greater Munich area because the A99 carries roughly 90,000 to 120,000 vehicles a day and there is no high-capacity parallel autobahn to absorb diverted flows.
- Measures to reduce chaos include early long-distance truck reroutes (for example advising trucks to use the A7 via Memmingen/Lindau for routes to Italy), temporary easing of some Mittlerer Ring diesel and truck restrictions, extra police on patrol, and advice to use public transport and avoid non-essential travel.
- Local access will be partly maintained: the B304 traffic will continue on a temporary bridge installed in August and junctions including Hohenbrunn, Ottobrunn and Haar will stay open, and a new permanent B304 bridge is planned for completion by the end of 2028.