A59 DüsseldorfMonheim Overhaul Begins With Full Closure Wednesday Night

Autobahn GmbH will renew 12 kilometres damaged by deteriorated concrete using wide detours plus demand‑controlled signals.

Overview

  • The A59 closes on October 15 at 21:00 between Dreieck Düsseldorf‑Süd and Richrath, extending to Monheim on October 20 for the first construction phase.
  • The initial phase is slated for about eight months, after which traffic will run single‑lane before work switches to the opposite direction toward Düsseldorf.
  • Works include full carriageway renewal along with repairs to bridges and drainage, plus modernization of road equipment across the 12‑kilometre segment.
  • Official long‑distance detours route drivers via A46–A3–A542 with an optimized flow at Autobahndreieck Langenfeld, and a second option via A46–A57–A1–A59.
  • Local diversions are signposted, with demand‑operated signals to regulate flow, and increased load is expected on alternative corridors such as the A3 and B8.