- Parliamentary State Secretary Christian Hirte announced at the A45 citizens’ festival near Rastplatz Hunscheid that traffic is expected to resume in February 2026.
- The target advances earlier projections that moved from summer 2026 to spring 2026 as construction accelerated.
- Hirte warned that adverse weather could delay sealing, paving and other final steps needed before the bridge can carry vehicles.
- Workers recently completed concreting the first bridge half, with remaining tasks including waterproofing, two-layer asphalt, edge elements, guardrails, signage and markings.
- The first completed structure is planned to carry two-way traffic initially, offering relief to Lüdenscheid after prolonged detours and economic losses estimated at well over €1 billion.