  • Rijkswaterstaat is running night works on the N839 near Bemmel and the A15 on‑ramp to build a temporary construction road for the planned A15 widening.
  • During those nights, drivers follow yellow detours via Bemmel while cyclists are routed via Plak and Dikelsestraat because the N839 path is closed, so Rijkswaterstaat urges extra travel time.
  • The A15 parallel carriageway between the Benelux and Vaanplein interchanges toward Rotterdam is closed this weekend for large‑scale asphalting, with the Heijplaat and Charlois on‑ramps remaining open.
  • The bridge over the Noord between Alblasserdam and Hendrik‑Ido‑Ambacht closes overnight for replacement of aging technical systems, and road traffic is diverted via the nearby Noordtunnel.
  • Metro track work in central Rotterdam splits service and closes Blaak, Oostplein and Gerdesiaweg through early May, with trams provided as an alternative on the affected stretch.